Location: Paragould Arkansas
Phase 1 – Submitted SWPPP, installed erosion control, built ~20,000 sq feet coffer cell, designed and installed dewatering system, excavated levee to new culvert elevation, constructed new culvert, reconstructed levee, and placed rip rap.
Phase 2 - Built second coffer cell around existing culvert, excavated levee to culvert elevation, removed existing culvert, and rebuilt second section of the levee.